Thomas County recently awarded Scruggs Company a $3.67 million contract for resurfacing and widening. Tentative start date for these projects is June 11, 2018. Scruggs Company will begin with Old 84 East and West. Your 2012 SPLOST is still at work for you!
Resurfacing
Click tab below for more Information on each road:
Old Hwy 84 West
1.15 miles of Old Hwy 84 West is to be resurfaced between Hwy 84 and Boston City limits
Old Hwy 84 East
2.67 miles of Old Hwy 84 East is to be resurfaced between Boston City limits and the Brooks County line
Whitney Camp Road
Whitney Camp Road is to be resurfaced between Boston City limits and the end of pavement on Whitney Camp for a total of 1.75 miles.
Widening and resurfacing:
Click tab below for more Information on each road:
Five Forks Road
Five Forks Road between Highway 84 and Coffee Road is to be widened and resurfaced. There is a total of 5.38 miles in this section of Five Forks Road.